Data Center Maintenance: Eastern PoP - 04/10: 1100 to 1500 EST
Scheduled Maintenance Report for net2phone Canada TRUST
Completed
The scheduled maintenance has been completed.
Posted Apr 10, 2024 - 15:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 10, 2024 - 11:00 EDT
Scheduled
Data Centre Technicians at our Eastern PoP (point-of-presence) will be performing routine facilities maintenance on Wednesday, April 10th between 11:00 a.m. and 3:00 p.m. EST.

Net2phone Canada Technicians will be monitoring during this vendor maintenance.

There is no expected impact from this maintenance. Calls and all other net2phone Canada services will operate as normal.
Posted Mar 28, 2024 - 09:08 EDT
This scheduled maintenance affected: Third Party.